Costs & Installation Guides
Costs & Installation Guides
Costs will be influenced by the following factors:
Location in SE QLD
Availability of parking on site
Access (if scaffold or scissor lift provided)
Voids or structural damage to existing structure (the preparation required)
Structural cracking – 0.2mm and above in zone of strengthening
Quantity of product required (larger volumes will reduce costs)
Power on site (3 phase)
Surface preparation required - Existing concrete quality affects the preparation required
Services in way
Steps in surface “From previous formwork”
After hours working required
Floor or soffit application
What to look for from an install contractor – before and after
QA Sheet – completed and signed on site (dirty site copy’s only)
Purchase invoice form suppliers for products used (note the grades of products)
Site Tap test results and void locations
Pull off tests before and after (3 before and 3 after) + one for each additional 100 m (photographic)
Check correct lengths and set out positions on site before, during and after
Check contractor owns their own pull off tester
All contractors staff are trained and ask for training program and sign offs
Check 3 previous client reference letters
Photos of preparation equipment
Photos of install equipment
Final report with photos
Installation Guide
Sika
Installation Guide
BASF
Installation Guide
Sika Wrap
Dry Application Guide
Sika Structural strenghtening
STRUCTURAL STRENGTHENING WITH SIKA SYSTEMS
Sika CarboShear
L System
Sika Wrap
Wet Application Guide
Sika CarboDur®
Near Surface Mounted Reinforcement
Sika CarboDur®
Externally Bonded Reinforcement
FREQUENTLY ASKED QUESTIONS
What about steps in the slab?
These can be incorporated with a competent contractor.
What about surface topping before?
This needs to be looked into, but can sometimes be laid over a topping – with sufficient pull off tests (topping dependent)
What about surface toppings afterwards?
We can advise on how to incorporate toppings
How far does the laminates protrude out from the surface?
Above – Depends on laminate
What about fire rating?
Don’t bother as it is expensive and not needed in 99.9% of times. Consultant should do a Rational Fire Design with min (DL+LL) and structure needs to have enough inherent capacity to withstand fire load case. In 99.9% of the time, this is OK and FRP does not need fire protection.
What about recessing and hitting existing reinforcing?
Reinforcing should be at least 20 mm below the surface- however this can be an issue and has happened in the past – we then liaise with the engineer and come up with a solution.
What happens is there is cracking in the existing structure?
We can rectify this using our specialist contractor experience in crack remedials and injection of a low viscosity resin.